We are delighted to provide an update on the ongoing construction of The Ismaili Center for the Jamat.

We are nearing completion of the building's superstructure (above ground), with Level 4 Decks nearly complete. Level 5 construction will be completed in the next four weeks approximately, bringing to completion the superstructure by the end of the year. 

Glass curtain walls have been installed at Levels 1st and 2nd for both the Education Wing and Social Wing.  Within the North Graden, landscape work continues in the Bayou Garden, the Gulzar Terrace, and the Eivan Terrace, with all North Garden concrete work to be completed by the end of the year.

We are dedicated to keeping the Jamat well-informed about our progress through regular video updates. Click here to watch the latest construction progress video.